Print Back to Calendar Return
    6.    
City Council Regular
Meeting Date: 08/15/2017  
Subject:    Approve Final Payment for Project 15-16, Sand Creek Park Buildings
Submitted For: Sharon Legg From: Dianne Nelson, Advanced Accounting Technician

INTRODUCTION
The City Engineer has recommended final payment for Project 15-16, Sand Creek Park Buildings, to several contractors.
DISCUSSION
A summary of contractors and final payment amounts for Project 15-16, Sand Creek Park Buildings, are outlined on the attached spreadsheet.
RECOMMENDATION
All of the dates and amounts are reasonable and accurate according to the project file.  No liquidated damages are recommended.  Staff recommends approval of the change orders and final payments according to the attached spreadsheet.

Attachments
Project 15-16 final payments

AgendaQuick©2005 - 2017 Destiny Software Inc., All Rights Reserved