Subject:    Parks Bond Project Updates
From: Ryan Gunderson

INTRODUCTION
Lions Coon Creek Park: 
Staff met with WSB to review the 90% Plans for the park.  Plans are being made to include public WiFi into the park for users.  Current plans are included for review.  Program is on schedule to go to Council in early February to authorize going out for bid and hopefully to award bids in late February or early March. 

Riverwind Park:
Rverwind park building renovation is wrapping up and should be open in early February.  Flooring was being laid this week and technology hook ups installed.  The building will include WiFi access for users.  Folding tables and chairs are being ordered for the rooms.  Capacity has been set for the rooms at:  56 for the old teen room (Room 2), 64 for the main room (Room 1), and 27 for the small room (Overflow room which was not updated. 

RECOMMENDATION
Staff asks the Commission to review Lions Park plans and express any comments or concerns.



Attachments
LionsParkPlans

AgendaQuick©2005 - 2019 Destiny Software Inc., All Rights Reserved