City Council Regular
Meeting Date: 09/03/2019  
Subject:    Approve Final Payment to Dryden Excavating, Inc. for Project 18-18, Pleasure Creek Culvert Extension
Submitted For: fhanson From: Dianne Nelson, Advanced Accounting Technician

INTRODUCTION
The City Engineer recommends final payment to Dryden Excavating, Inc. for Project 18-18, Pleasure Creek Culvert Extension.
DISCUSSION
A summary of Project 18-18 is as follows:
 
Substantial completion date 6/28/19
Contract completion date 6/28/19
Actual completion date 6/28/19
 
Contract amount $129,244.96
Total additions/deletions $0.00
Final contract amount $129,244.96
Actual project costs $127,879.78
Less:  previous payments by City ($106,628.23)
Amount due $21,251.55
Amount under final contract $1,365.18
The actual project costs were less than the final contract amount due to quantity adjustments from the original bid.
 
RECOMMENDATION
Staff recommends approval of the final payment to Dryden Excavating, Inc. in the amount of $21,251.55 for Project 18-18, Pleasure Creek Culvert Extension.